Gathering System Planning
Gas plant Construction and sizing for the second phase of a shale gas drilling program
Challenges:
- Second phase reserves and number of pads still variable
- Gas plant capacity planning is required for different sizing scenarios
Flow Diagram – Gathering System Planning
The gathering system for the second phase of the development project is under consideration, including the size of the gas plant and the number of pads to drill

The development plan for the second phase of development includes construction of a second gas plant and a second pad drilling program
The generation of a new what-if scenario can be done in a few minutes:
1 Copy the base scenario
2 Input the new key parameters to the development scenario
3 Calculate and Compare

The Key Parameters for the Second Phase of Development is Managed Through User Data


Comparing the different development scenarios can be conducted on an incremental basis
Scenario 1 (Baseline) Phase 1 - 50 MMCFPD Phase 2 – 100 MMCFPD |
Scenario 2 (‘What-If’) Phase 1 - 50 MMCFPD Phase 2 – 150 MMCFPD |

Incremental Results
Scenario 2 – Scenario 1

Including generating the key economic indicators to compare the options
WellSpring quantifies the economics of your gathering system options in one integrated application

Incremental Economic Indicators